SHEET PILING FOR NEW QUAY IS BEING SET

07/11/2016

The new quay is constructed with a combination wall, consisting of steel pipes and steel sheet piling.

All pipes for the new 600 metres quay have been set, and the work with setting of the steel sheet piling between the pipes was started in week 44.

The work with setting the sheet piling is carried out by means of vibration – a method, which does not cause noise in the same way as the ramming, where the piling is hammered into place.

We therefore do not expect any noise nuisance of significance.